A useful bathroom fixture checklist defines the exact products, their installation interfaces and when each component is needed on site. Record visible fittings and concealed parts separately, link them to the same room and drawing revision, and compare quotations against that schedule. Product photos and a generic delivery estimate are not a complete specification.
This guide is for homeowners, designers and project buyers preparing a coordinated bathroom order. Start with the George bathroom fixture buying hub to browse product families, then use the fields below to turn a shortlist into a quotation brief.

What belongs in a bathroom fixture schedule?
Use one item code for each distinct configuration. A change in mounting, finish, basin size, toilet outlet or included accessories can require a separate line. Repeat the approved line by room type and quantity instead of relying on a catalogue page to identify a whole project package.
The following is a field template for your own specification, not a completed George order. Leave unknown values marked for confirmation. Assign a reviewer and revision so unresolved details remain visible before purchase.
| Field | Information to record | Check before approval |
|---|---|---|
| Room and item | Room type, fixture code, quantity, drawing and revision | Quantities agree with the latest room schedule |
| Product identity | Manufacturer, model and configuration | The quoted item matches the selected technical drawing |
| Mounting and dimensions | Mounting method, overall size, set-out reference, cut-outs and access | The drawing reference and finished surface build-up are coordinated |
| Connections | Supply and waste details; electrical needs where applicable | The project installer has checked the exact model information |
| Finish and care | Finish code, sample reference, visible surfaces and cleaning instructions | Proposed substitutions and sample differences are recorded |
| Complete assembly | Visible fittings, concealed body, carrier, waste, fixings and accessories as applicable | Included and separately supplied components are explicit |
| Documents | Applicable destination requirements, model evidence and reviewer | The evidence applies to the selected product |
| Delivery and terms | Required on site date, lead time basis, packing, freight and written warranty | Dates, responsibilities and exclusions are agreed |

Coordinate the fixture before approving finishes or cut-outs
Basins, taps and bathroom cabinets
Review the basin and tap as a pair. Check the outlet position against the usable bowl, mounting holes, rim and splash exposure using the selected products. Coordinate the waste and trap with drawers, shelves and service access. Record whether a dimension is measured from the structural surface or the finished face; use the manufacturer’s stated reference.
For wall mounted taps, compare the permitted installation depth with the actual wall build-up and the proposed service arrangement. Do not use one universal tap height or spout clearance for every basin.
Remember to check: our wall mounted vs deck mounted taps guide explains which parts of this decision need to be coordinated before closing the wall or drilling the countertop.
Shower sets, valves and glass
List the shower outlets, controls, trim, concealed valve and installation parts separately. Obtain the manufacturer’s compatibility list for the actual combination. A finish name or similar handle shape does not identify a matching valve. As a manufacturer example, the Delta MultiChoice installation document gives instructions for its own valve and trim system; it is not evidence for an unrelated product.
Ask the plumbing team to review supply conditions, simultaneous outlets, drainage and the selected valve’s operating requirements. Coordinate glass openings, fixing locations and maintenance access with the room drawings and waterproofing details. Use the actual installation instructions and project requirements for testing and commissioning.
Preparing a bathroom package for a home, hotel or multi-unit project? Send George the room drawings, item schedule and destination so the proposed products and included components can be identified before quotations are compared.
Get a Free Quote
Toilets, baths and lighting
For a toilet, identify its mounting, outlet arrangement, cistern or flushing system, seat and any required carrier or electrical supply. Confirm the chosen assembly’s drawings rather than assuming one rough-in dimension or wall cavity suits every product.
For a bath, record outside dimensions, the usable interior, filling and drainage arrangements, model-specific load information, delivery route and maintenance space. The two person tub buying checklist helps organise these questions. Confirm the actual manufacturer and model; Jacuzzi is a brand name.
Coordinate mirror and lighting positions with the vanity and tap layout. Ask the project electrical designer or installer to select fixtures and protection suitable for their actual locations and local requirements. Do not treat an IP rating and a North American location marking as interchangeable worldwide approvals.
Match documents to the destination and exact model
Start with the destination, building use and project specification. Ask the responsible project team to identify the applicable requirements, then collect the relevant model drawings, installation manuals and listing or registration evidence. Avoid a single checklist that labels every certification mandatory for every country.
Australia: WaterMark and WELS serve different purposes. The Australian government’s consumer protection guidance explains plumbing product certification and water efficiency registration, including product categories that require both. Confirm the exact model and scope using the official records. Our WaterMark vs WELS guide provides the purchasing workflow.
United States: if WaterSense is specified, use the EPA label guidance and product search to check eligible products and the selected model. The label addresses EPA water efficiency and performance criteria with independent certification; it is not a substitute for checking the project’s other plumbing or accessibility requirements.
A brand brochure, certificate for another model or claimed factory capability does not establish the status of every fixture in the order. Record who checked each document and when, and resolve mismatches before release.

Plan deliveries around construction milestones
Work backwards from the contractor’s actual programme. There is no universal eight to twelve week gap between concealed components and visible fittings. Factory availability, document approval, shipping, customs, site readiness and storage all affect the order dates.
| Milestone | Coordinate before it | Confirm in writing |
|---|---|---|
| Before order release | Models, samples, documents, quantities and drawing revisions | Approved scope and unresolved items |
| Before wall closure or concealed work | Valves, carriers, supports and other components required by the chosen assembly | Required on site dates, installer review and inspection requirements |
| Before cutting or drilling finishes | Actual templates and coordinated product dimensions | Approved cut-outs, mounting and access details |
| Before final installation | Visible fittings, compatible parts, protected storage and installation instructions | Delivery completeness, damage checks and installation responsibilities |
| At handover | Commissioning, care information, spare parts and written warranty | Records, contacts and agreed outstanding work |
Where a phased shipment is needed, identify its items and packing list explicitly. Compare the extra freight and handling with site storage and programme needs. Agree changes before goods are dispatched rather than assuming every bathroom order must use the same shipping arrangement.
Check the quotation before releasing the bathroom package
- Every room and item code has the correct quantity and latest drawing revision.
- The model, finish, mounting and document references match the proposed goods.
- Visible trim, concealed parts and accessories are individually included or excluded.
- The project team has reviewed interfaces, access, utilities and installation requirements.
- Substitutions are identified and approved against the same specification.
- Packing, freight, destination, delivery milestones and written warranty terms are recorded.
Compare quotations on this common scope. A lower total can reflect missing valve bodies, wastes, carriers, installation parts or delivery services rather than a better price for the same package.
Ready to discuss your bathroom package? Send George the destination, room drawings, fixture schedule, quantities, finish references and required on site dates. Identify any model or document still awaiting confirmation so it can be resolved before order approval.
Get a Free QuoteFrequently asked questions
What should a bathroom fixture specification include?
Record the room and item code, quantity, exact manufacturer and model, finish, mounting method, dimension drawing, connections, included parts, required documents and delivery milestone. Keep the approved revision and identify information still awaiting confirmation.
Should concealed valves and visible fittings arrive together?
Use the site programme to decide. Concealed items may be needed before wall closure, while visible fittings may be installed later. Confirm each required on site date, compatible component list and storage arrangement; there is no universal number of weeks between deliveries.
Can any shower trim fit an existing valve?
Do not assume compatibility. Identify the installed valve and the proposed trim model, then obtain the manufacturer’s compatibility information and installation instructions. Similar appearance or a matching brand name alone is not enough.
Does one sanitary ware certificate cover the whole order?
Do not assume it does. Match each required listing or registration to the exact product, model and destination. Check product scope and current status with the relevant official source; a supplier brochure or unrelated model certificate does not establish the status of the selected items.
What should I send George for a bathroom package quotation?
Send the project destination, room drawings and revision, fixture schedule, quantities, finish references, required documents and delivery milestones. Ask for visible products, concealed parts, accessories, exclusions, packing and freight terms to be itemised.